Road closure during works from 13th November until 4th December

Published: 13 November 2023

1st Stage at Selling Road / Fox Lane junction to kerb around the corner, re-site drains and repair damaged road edge commences 13th November and is expected to be complete on 4th December. One half of the triangle junction will be closed during the works, but access will remain using the other side of the triangle junction.

2nd Stage between Monica Close and Fox Lane is programmed to commence on 2nd January 2024 and is expected to be completed by 6th February 2023. This will be for the installation of the additional drainage on Selling Road to help prevent water flowing around into Fox Lane from the south. This will be a full road closure and therefore there will be no access for through traffic. A signed diversion will be in place.